Information
Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
- Question 1 of 30
1. Question
Which quality management tool is used to prioritize problem areas to focus improvement efforts based on the principle that 80% of problems are often caused by 20% of the issues?
CorrectA Pareto Chart is used in quality management to prioritize problem areas based on the Pareto Principle, which states that 80% of problems are often caused by 20% of the issues. According to the PMBOK® Guide, Pareto Charts help project teams identify and focus on the most significant contributors to issues or defects, allowing them to allocate resources effectively for improvement efforts. This tool enables project managers to target efforts where they will have the greatest impact on enhancing project quality.
IncorrectA Pareto Chart is used in quality management to prioritize problem areas based on the Pareto Principle, which states that 80% of problems are often caused by 20% of the issues. According to the PMBOK® Guide, Pareto Charts help project teams identify and focus on the most significant contributors to issues or defects, allowing them to allocate resources effectively for improvement efforts. This tool enables project managers to target efforts where they will have the greatest impact on enhancing project quality.
- Question 2 of 30
2. Question
Tom is managing a construction project that requires specialized equipment. He decides to contract with a supplier who offers the best value for money, considering both cost and performance factors. Which procurement strategy is Tom employing?
CorrectTom is employing the Best Value procurement strategy, which involves selecting a supplier based on a combination of cost and performance factors to achieve the best overall value. According to the PMBOK® Guide, Best Value procurement considers not only the price but also other criteria such as quality, past performance, technical capability, and risk management approach. This approach ensures that Tom’s project obtains the most advantageous supplier offering, balancing cost-effectiveness with the capability to meet project requirements.
IncorrectTom is employing the Best Value procurement strategy, which involves selecting a supplier based on a combination of cost and performance factors to achieve the best overall value. According to the PMBOK® Guide, Best Value procurement considers not only the price but also other criteria such as quality, past performance, technical capability, and risk management approach. This approach ensures that Tom’s project obtains the most advantageous supplier offering, balancing cost-effectiveness with the capability to meet project requirements.
- Question 3 of 30
3. Question
Which ethical principle emphasizes treating all stakeholders fairly and balancing their needs and interests in project decisions?
CorrectThe ethical principle of Fairness emphasizes treating all stakeholders fairly and balancing their needs and interests in project decisions. According to the PMI Code of Ethics and Professional Conduct, project managers are expected to make decisions impartially, without favoritism or bias, to ensure equitable treatment of all parties involved. Fairness contributes to maintaining trust and credibility with stakeholders and upholds ethical standards in project management practices.
IncorrectThe ethical principle of Fairness emphasizes treating all stakeholders fairly and balancing their needs and interests in project decisions. According to the PMI Code of Ethics and Professional Conduct, project managers are expected to make decisions impartially, without favoritism or bias, to ensure equitable treatment of all parties involved. Fairness contributes to maintaining trust and credibility with stakeholders and upholds ethical standards in project management practices.
- Question 4 of 30
4. Question
Which of the following techniques is used to determine the budget by aggregating the estimated costs of individual activities or work packages to establish a cost baseline?
CorrectBottom-Up Estimating is used to determine the budget by aggregating the estimated costs of individual activities or work packages to establish a cost baseline. According to the PMBOK® Guide, this technique involves estimating the cost of each component of the work breakdown structure (WBS) and summing them to get the total project cost. Bottom-Up Estimating is detailed and accurate, making it ideal for complex projects where precise cost control is necessary.
IncorrectBottom-Up Estimating is used to determine the budget by aggregating the estimated costs of individual activities or work packages to establish a cost baseline. According to the PMBOK® Guide, this technique involves estimating the cost of each component of the work breakdown structure (WBS) and summing them to get the total project cost. Bottom-Up Estimating is detailed and accurate, making it ideal for complex projects where precise cost control is necessary.
- Question 5 of 30
5. Question
Jane is managing a large IT project. She notices that team members are experiencing conflicts due to unclear roles and responsibilities. What should Jane do to address this issue?
CorrectJane should update the resource management plan to clarify roles and responsibilities. According to the PMBOK® Guide, the resource management plan includes details about team roles, responsibilities, authority, and competencies. By providing clear definitions of roles and responsibilities, Jane can reduce conflicts, improve coordination, and enhance team performance. This approach ensures that team members understand their tasks and how they contribute to the project’s success.
IncorrectJane should update the resource management plan to clarify roles and responsibilities. According to the PMBOK® Guide, the resource management plan includes details about team roles, responsibilities, authority, and competencies. By providing clear definitions of roles and responsibilities, Jane can reduce conflicts, improve coordination, and enhance team performance. This approach ensures that team members understand their tasks and how they contribute to the project’s success.
- Question 6 of 30
6. Question
Which of the following risk response strategies is used to deal with positive risks or opportunities?
CorrectThe Enhance risk response strategy is used to deal with positive risks or opportunities. According to the PMBOK® Guide, enhancing involves increasing the probability or impact of an opportunity to ensure it is realized. This strategy focuses on proactive actions to maximize the potential benefits of positive risks. By enhancing opportunities, project managers can improve project outcomes and achieve greater value from potential positive events.
IncorrectThe Enhance risk response strategy is used to deal with positive risks or opportunities. According to the PMBOK® Guide, enhancing involves increasing the probability or impact of an opportunity to ensure it is realized. This strategy focuses on proactive actions to maximize the potential benefits of positive risks. By enhancing opportunities, project managers can improve project outcomes and achieve greater value from potential positive events.
- Question 7 of 30
7. Question
Which process involves tracking, reviewing, and regulating the progress and performance of the project and identifying any areas where changes to the plan are required?
CorrectThe process of Monitor and Control Project Work involves tracking, reviewing, and regulating the progress and performance of the project and identifying any areas where changes to the plan are required. According to the PMBOK® Guide, this process ensures that project objectives are met by monitoring project activities and performance to identify variances from the plan. This helps in making informed decisions to correct issues and maintain control over the project.
IncorrectThe process of Monitor and Control Project Work involves tracking, reviewing, and regulating the progress and performance of the project and identifying any areas where changes to the plan are required. According to the PMBOK® Guide, this process ensures that project objectives are met by monitoring project activities and performance to identify variances from the plan. This helps in making informed decisions to correct issues and maintain control over the project.
- Question 8 of 30
8. Question
Alex is managing a product development project. Due to a delay in receiving critical components from a supplier, the project schedule is at risk. What should Alex do to address this delay?
CorrectApplying resource leveling to adjust the schedule is an appropriate action to address the delay. According to the PMBOK® Guide, resource leveling is a technique that adjusts the project schedule to account for resource constraints. By redistributing resources and adjusting activities, Alex can create a more realistic schedule that accommodates the delay without compromising project objectives. This proactive approach helps in maintaining project control and managing time effectively.
IncorrectApplying resource leveling to adjust the schedule is an appropriate action to address the delay. According to the PMBOK® Guide, resource leveling is a technique that adjusts the project schedule to account for resource constraints. By redistributing resources and adjusting activities, Alex can create a more realistic schedule that accommodates the delay without compromising project objectives. This proactive approach helps in maintaining project control and managing time effectively.
- Question 9 of 30
9. Question
Which process involves identifying all people or organizations impacted by the project and documenting relevant information regarding their interests, involvement, and impact on project success?
CorrectThe Identify Stakeholders process involves identifying all people or organizations impacted by the project and documenting relevant information regarding their interests, involvement, and impact on project success. According to the PMBOK® Guide, this process is crucial for understanding who the stakeholders are and how they might influence or be influenced by the project. Early identification and analysis of stakeholders help in developing effective strategies for engaging them throughout the project lifecycle.
IncorrectThe Identify Stakeholders process involves identifying all people or organizations impacted by the project and documenting relevant information regarding their interests, involvement, and impact on project success. According to the PMBOK® Guide, this process is crucial for understanding who the stakeholders are and how they might influence or be influenced by the project. Early identification and analysis of stakeholders help in developing effective strategies for engaging them throughout the project lifecycle.
- Question 10 of 30
10. Question
Which cost estimation technique uses historical data from similar projects and adjusts for differences to estimate the costs of the current project?
CorrectAnalogous Estimating uses historical data from similar projects and adjusts for differences to estimate the costs of the current project. According to the PMBOK® Guide, this technique relies on expert judgment and is often used when there is limited information available about the project. It is a quicker and less costly method than other estimation techniques, although it may be less accurate.
IncorrectAnalogous Estimating uses historical data from similar projects and adjusts for differences to estimate the costs of the current project. According to the PMBOK® Guide, this technique relies on expert judgment and is often used when there is limited information available about the project. It is a quicker and less costly method than other estimation techniques, although it may be less accurate.
- Question 11 of 30
11. Question
Lisa is managing a software development project. During a team meeting, she notices that one team member, who is an expert in a critical area, is consistently overburdened with tasks. What should Lisa do to address this resource overallocation?
CorrectReassigning some of the tasks to other team members to balance the workload is the best approach to address resource overallocation. According to the PMBOK® Guide, effective resource management involves ensuring that no team member is overburdened and that tasks are distributed evenly across the team. This helps in maintaining team morale, avoiding burnout, and ensuring that the project progresses smoothly without delays.
IncorrectReassigning some of the tasks to other team members to balance the workload is the best approach to address resource overallocation. According to the PMBOK® Guide, effective resource management involves ensuring that no team member is overburdened and that tasks are distributed evenly across the team. This helps in maintaining team morale, avoiding burnout, and ensuring that the project progresses smoothly without delays.
- Question 12 of 30
12. Question
Which risk identification technique involves a structured, systematic review of project documentation, including plans and assumptions, to identify potential risks?
CorrectDocument Analysis is a risk identification technique that involves a structured, systematic review of project documentation, including plans and assumptions, to identify potential risks. According to the PMBOK® Guide, this technique helps uncover risks that might not be immediately obvious by examining project documents such as project plans, assumptions logs, and historical records. This comprehensive review ensures that potential risks are identified early in the project planning phase, allowing for better risk management and mitigation strategies.
IncorrectDocument Analysis is a risk identification technique that involves a structured, systematic review of project documentation, including plans and assumptions, to identify potential risks. According to the PMBOK® Guide, this technique helps uncover risks that might not be immediately obvious by examining project documents such as project plans, assumptions logs, and historical records. This comprehensive review ensures that potential risks are identified early in the project planning phase, allowing for better risk management and mitigation strategies.
- Question 13 of 30
13. Question
Which communication model component represents the method used to convey the message from the sender to the receiver?
CorrectThe medium is the component of the communication model that represents the method used to convey the message from the sender to the receiver. According to the PMBOK® Guide, the medium can include various channels such as emails, meetings, reports, or phone calls. Choosing the appropriate medium is crucial for ensuring that the message is effectively communicated and understood by the intended audience.
IncorrectThe medium is the component of the communication model that represents the method used to convey the message from the sender to the receiver. According to the PMBOK® Guide, the medium can include various channels such as emails, meetings, reports, or phone calls. Choosing the appropriate medium is crucial for ensuring that the message is effectively communicated and understood by the intended audience.
- Question 14 of 30
14. Question
During the final quality inspection of a manufacturing project, Emily discovers that several units of the product do not meet the specified quality standards. What should Emily do first to address this quality issue?
CorrectPerforming a root cause analysis to identify the source of the defects is the first step Emily should take to address the quality issue. According to the PMBOK® Guide, root cause analysis helps to determine the underlying reasons for the defects, which is essential for implementing effective corrective actions. By understanding the cause, Emily can prevent similar issues in future production cycles and ensure that the project meets the required quality standards.
IncorrectPerforming a root cause analysis to identify the source of the defects is the first step Emily should take to address the quality issue. According to the PMBOK® Guide, root cause analysis helps to determine the underlying reasons for the defects, which is essential for implementing effective corrective actions. By understanding the cause, Emily can prevent similar issues in future production cycles and ensure that the project meets the required quality standards.
- Question 15 of 30
15. Question
Which tool or technique involves visually representing the sequence of project activities and their dependencies?
CorrectA Network Diagram is a tool or technique that involves visually representing the sequence of project activities and their dependencies. According to the PMBOK® Guide, Network Diagrams help project managers understand the logical relationships between tasks, identify the critical path, and plan the project schedule effectively. This visual representation is essential for analyzing the flow of activities and ensuring that all dependencies are accounted for in the project plan.
IncorrectA Network Diagram is a tool or technique that involves visually representing the sequence of project activities and their dependencies. According to the PMBOK® Guide, Network Diagrams help project managers understand the logical relationships between tasks, identify the critical path, and plan the project schedule effectively. This visual representation is essential for analyzing the flow of activities and ensuring that all dependencies are accounted for in the project plan.
- Question 16 of 30
16. Question
Which document formally authorizes a project or a phase and provides the project manager with the authority to apply organizational resources to project activities?
CorrectThe Project Charter formally authorizes a project or a phase and provides the project manager with the authority to apply organizational resources to project activities. According to the PMBOK® Guide, the Project Charter includes key information such as the project purpose, objectives, high-level requirements, assumptions, constraints, and stakeholders. It serves as a reference document throughout the project lifecycle and ensures that all stakeholders have a clear understanding of the project’s goals and parameters.
IncorrectThe Project Charter formally authorizes a project or a phase and provides the project manager with the authority to apply organizational resources to project activities. According to the PMBOK® Guide, the Project Charter includes key information such as the project purpose, objectives, high-level requirements, assumptions, constraints, and stakeholders. It serves as a reference document throughout the project lifecycle and ensures that all stakeholders have a clear understanding of the project’s goals and parameters.
- Question 17 of 30
17. Question
During the planning phase of a construction project, Sarah identifies a potential risk that heavy rainfall could delay the project. What should Sarah do to minimize the impact of this risk?
CorrectCreating a contingency plan that includes additional time for weather delays is the appropriate response to minimize the impact of the risk. According to the PMBOK® Guide, contingency planning involves developing responses in advance to deal with risks that have been identified. By including extra time in the project schedule, Sarah can ensure that the project remains on track even if heavy rainfall occurs, thereby mitigating the risk of delays.
IncorrectCreating a contingency plan that includes additional time for weather delays is the appropriate response to minimize the impact of the risk. According to the PMBOK® Guide, contingency planning involves developing responses in advance to deal with risks that have been identified. By including extra time in the project schedule, Sarah can ensure that the project remains on track even if heavy rainfall occurs, thereby mitigating the risk of delays.
- Question 18 of 30
18. Question
Which stakeholder analysis technique involves grouping stakeholders based on their level of power, interest, and influence?
CorrectThe Power/Interest Grid is a stakeholder analysis technique that involves grouping stakeholders based on their level of power, interest, and influence. According to the PMBOK® Guide, this tool helps project managers prioritize stakeholders and tailor their engagement strategies. By understanding the power and interest levels of stakeholders, project managers can effectively manage stakeholder expectations, communication, and involvement, ensuring that the project meets their needs and gains their support.
IncorrectThe Power/Interest Grid is a stakeholder analysis technique that involves grouping stakeholders based on their level of power, interest, and influence. According to the PMBOK® Guide, this tool helps project managers prioritize stakeholders and tailor their engagement strategies. By understanding the power and interest levels of stakeholders, project managers can effectively manage stakeholder expectations, communication, and involvement, ensuring that the project meets their needs and gains their support.
- Question 19 of 30
19. Question
Which process involves formalizing acceptance of the completed project deliverables?
CorrectThe Validate Scope process involves formalizing acceptance of the completed project deliverables. According to the PMBOK® Guide, this process entails reviewing deliverables with the customer or sponsor to ensure they meet the required specifications and obtaining formal acceptance. It ensures that the project deliverables are completed satisfactorily and that any changes or discrepancies are addressed before closing the project or phase.
IncorrectThe Validate Scope process involves formalizing acceptance of the completed project deliverables. According to the PMBOK® Guide, this process entails reviewing deliverables with the customer or sponsor to ensure they meet the required specifications and obtaining formal acceptance. It ensures that the project deliverables are completed satisfactorily and that any changes or discrepancies are addressed before closing the project or phase.
- Question 20 of 30
20. Question
During a quality audit, it is found that several components of a new software application do not meet the specified quality standards. As the project manager, David needs to address these issues. What should David do first?
CorrectConducting a quality control process to identify the root cause is the first step David should take to address the quality issues. According to the PMBOK® Guide, quality control involves monitoring and recording results of quality activities to assess performance and recommend necessary changes. By identifying the root cause, David can implement effective corrective actions to resolve the issues and prevent them from recurring, ensuring the software application meets the required quality standards.
IncorrectConducting a quality control process to identify the root cause is the first step David should take to address the quality issues. According to the PMBOK® Guide, quality control involves monitoring and recording results of quality activities to assess performance and recommend necessary changes. By identifying the root cause, David can implement effective corrective actions to resolve the issues and prevent them from recurring, ensuring the software application meets the required quality standards.
- Question 21 of 30
21. Question
Which communication method is most suitable for urgent and complex project issues that require immediate discussion and resolution?
CorrectVideo Conference is the most suitable communication method for urgent and complex project issues that require immediate discussion and resolution. According to the PMBOK® Guide, video conferences provide real-time, face-to-face interaction, which is essential for addressing complex issues quickly and effectively. This method allows for instant feedback, clarifications, and collaborative problem-solving, making it ideal for situations where timely decision-making is critical.
IncorrectVideo Conference is the most suitable communication method for urgent and complex project issues that require immediate discussion and resolution. According to the PMBOK® Guide, video conferences provide real-time, face-to-face interaction, which is essential for addressing complex issues quickly and effectively. This method allows for instant feedback, clarifications, and collaborative problem-solving, making it ideal for situations where timely decision-making is critical.
- Question 22 of 30
22. Question
Which type of contract involves the seller being paid for all allowed costs to perform the contract plus a fixed fee payment calculated as a percentage of the initial estimated project costs?
CorrectA Cost Plus Fixed Fee (CPFF) contract involves the seller being paid for all allowed costs to perform the contract plus a fixed fee payment calculated as a percentage of the initial estimated project costs. According to the PMBOK® Guide, this type of contract provides a fixed fee as an incentive for the seller, regardless of performance, ensuring that the seller is compensated for their effort and covering the costs incurred. This contract type is typically used when costs cannot be accurately estimated at the outset.
IncorrectA Cost Plus Fixed Fee (CPFF) contract involves the seller being paid for all allowed costs to perform the contract plus a fixed fee payment calculated as a percentage of the initial estimated project costs. According to the PMBOK® Guide, this type of contract provides a fixed fee as an incentive for the seller, regardless of performance, ensuring that the seller is compensated for their effort and covering the costs incurred. This contract type is typically used when costs cannot be accurately estimated at the outset.
- Question 23 of 30
23. Question
During the implementation of a marketing campaign, Maria identifies a significant opportunity to leverage social media influencers to increase brand visibility. What should Maria do to take advantage of this opportunity?
CorrectEnhancing the opportunity by increasing the budget for social media influencers is the appropriate action Maria should take. According to the PMBOK® Guide, enhancing involves increasing the probability or impact of an opportunity to ensure it is realized. By allocating more resources to leverage social media influencers, Maria can maximize the potential benefits of this opportunity, leading to greater brand visibility and potentially higher returns on the marketing campaign.
IncorrectEnhancing the opportunity by increasing the budget for social media influencers is the appropriate action Maria should take. According to the PMBOK® Guide, enhancing involves increasing the probability or impact of an opportunity to ensure it is realized. By allocating more resources to leverage social media influencers, Maria can maximize the potential benefits of this opportunity, leading to greater brand visibility and potentially higher returns on the marketing campaign.
- Question 24 of 30
24. Question
Which conflict resolution technique involves finding a solution that partially satisfies both parties?
CorrectCompromising is a conflict resolution technique that involves finding a solution that partially satisfies both parties. According to the PMBOK® Guide, this technique seeks a middle ground where each party gives up something to reach a mutually acceptable agreement. While it may not fully satisfy all parties, compromising can be an effective way to resolve conflicts quickly and maintain working relationships within the project team.
IncorrectCompromising is a conflict resolution technique that involves finding a solution that partially satisfies both parties. According to the PMBOK® Guide, this technique seeks a middle ground where each party gives up something to reach a mutually acceptable agreement. While it may not fully satisfy all parties, compromising can be an effective way to resolve conflicts quickly and maintain working relationships within the project team.
- Question 25 of 30
25. Question
Which technique is used to identify the longest sequence of activities that determines the shortest possible duration for the project?
CorrectThe Critical Path Method (CPM) is used to identify the longest sequence of activities that determines the shortest possible duration for the project. According to the PMBOK® Guide, the critical path is the longest path through the project schedule network diagram and determines the shortest time in which the project can be completed. Activities on the critical path have zero slack, meaning any delay in these activities will delay the entire project.
IncorrectThe Critical Path Method (CPM) is used to identify the longest sequence of activities that determines the shortest possible duration for the project. According to the PMBOK® Guide, the critical path is the longest path through the project schedule network diagram and determines the shortest time in which the project can be completed. Activities on the critical path have zero slack, meaning any delay in these activities will delay the entire project.
- Question 26 of 30
26. Question
During a software development project, John identifies a high probability of scope creep due to frequent changes in requirements from the client. What should John do to manage this risk?
CorrectImplementing strict change control procedures to manage requirements changes is the appropriate action to manage the risk of scope creep. According to the PMBOK® Guide, change control procedures help ensure that all changes are properly documented, reviewed, and approved before implementation. This helps prevent unauthorized changes and ensures that any changes to the project scope are carefully considered, minimizing the impact of scope creep on the project.
IncorrectImplementing strict change control procedures to manage requirements changes is the appropriate action to manage the risk of scope creep. According to the PMBOK® Guide, change control procedures help ensure that all changes are properly documented, reviewed, and approved before implementation. This helps prevent unauthorized changes and ensures that any changes to the project scope are carefully considered, minimizing the impact of scope creep on the project.
- Question 27 of 30
27. Question
Which process involves obtaining seller responses, selecting a seller, and awarding a contract?
CorrectThe Conduct Procurements process involves obtaining seller responses, selecting a seller, and awarding a contract. According to the PMBOK® Guide, this process includes activities such as preparing procurement documents, conducting bidder conferences, evaluating proposals, and negotiating contracts. The objective is to select the most qualified seller and establish agreements that define the responsibilities and terms for providing the required goods or services for the project.
IncorrectThe Conduct Procurements process involves obtaining seller responses, selecting a seller, and awarding a contract. According to the PMBOK® Guide, this process includes activities such as preparing procurement documents, conducting bidder conferences, evaluating proposals, and negotiating contracts. The objective is to select the most qualified seller and establish agreements that define the responsibilities and terms for providing the required goods or services for the project.
- Question 28 of 30
28. Question
Which quality management process involves monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations?
CorrectControl Quality involves monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. According to the PMBOK® Guide, this process includes inspecting deliverables, identifying defects, and ensuring that project work is aligned with the quality requirements. It provides data and information about the quality of project deliverables and necessary improvements.
IncorrectControl Quality involves monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. According to the PMBOK® Guide, this process includes inspecting deliverables, identifying defects, and ensuring that project work is aligned with the quality requirements. It provides data and information about the quality of project deliverables and necessary improvements.
- Question 29 of 30
29. Question
During the execution phase of an IT project, Anna notices that one of the key stakeholders, who was initially supportive, is now showing resistance to the project’s progress. What should Anna do to manage this stakeholder’s engagement effectively?
CorrectScheduling a meeting with the stakeholder to understand and address their concerns is the best course of action. According to the PMBOK® Guide, effective stakeholder management involves engaging stakeholders based on their needs, expectations, interests, and potential impact on project success. By addressing the stakeholder’s concerns, Anna can foster a positive relationship, mitigate resistance, and gain the necessary support for project progress.
IncorrectScheduling a meeting with the stakeholder to understand and address their concerns is the best course of action. According to the PMBOK® Guide, effective stakeholder management involves engaging stakeholders based on their needs, expectations, interests, and potential impact on project success. By addressing the stakeholder’s concerns, Anna can foster a positive relationship, mitigate resistance, and gain the necessary support for project progress.
- Question 30 of 30
30. Question
Which communication technique is most effective for ensuring that complex and sensitive project information is understood by stakeholders?
CorrectFace-to-Face Meetings are the most effective communication technique for ensuring that complex and sensitive project information is understood by stakeholders. According to the PMBOK® Guide, face-to-face interactions allow for immediate feedback, clarification of misunderstandings, and addressing concerns in real-time. This method is particularly important for conveying complex information and resolving sensitive issues, as it helps ensure clear communication and builds trust among stakeholders.
IncorrectFace-to-Face Meetings are the most effective communication technique for ensuring that complex and sensitive project information is understood by stakeholders. According to the PMBOK® Guide, face-to-face interactions allow for immediate feedback, clarification of misunderstandings, and addressing concerns in real-time. This method is particularly important for conveying complex information and resolving sensitive issues, as it helps ensure clear communication and builds trust among stakeholders.