Microsoft Project Certification Exam Study Flashcard
Learn about below frequently tested concepts via flashcard
Last Updated: September 2024
Question:
Define "Fixed Cost" in Microsoft Project.
Answer:
Fixed Cost refers to a cost that does not change regardless of the amount of work or duration of the task. It is a set amount that is assigned to a task or project and remains constant.
Question:
Define the term “Lag Time” in the context of Microsoft Project.
Answer:
Lag Time is a delay between the end of one task and the start of a dependent task. It is a positive value that delays the start of the successor task.
Question:
Describe "Work Resource" and its role in Microsoft Project.
Answer:
A Work Resource is a type of resource that performs work on tasks, such as employees or equipment. Work Resources are allocated to tasks and their availability affects task scheduling and project planning.
Question:
Describe how "Project Calendar" settings impact task scheduling.
Answer:
The Project Calendar defines the working days and hours for the entire project. It affects task scheduling by determining which days are considered workdays and how task durations are calculated.
Question:
Describe the function of "Resource Graph View" in Microsoft Project.
Answer:
The Resource Graph View displays a visual representation of resource allocation over time. It helps in identifying periods of over-allocation and under-allocation for effective resource management.
Question:
Describe the function of "Task Inspector" in Microsoft Project.
Answer:
The Task Inspector helps identify issues and conflicts with tasks, such as scheduling problems or resource conflicts, and provides recommendations for resolving these issues.
Question:
Describe the role of "Budget Resources" in Microsoft Project.
Answer:
Budget Resources are used to track and manage budgeted costs and financial aspects of the project. They represent costs that are not associated with specific tasks but with the overall project budget.
Question:
Explain "Cost Variance" and how it is calculated in Microsoft Project.
Answer:
Cost Variance (CV) measures the difference between the earned value and the actual cost of work performed. It is calculated as CV = EV - AC, where EV is Earned Value and AC is Actual Cost.
Question:
Explain "Duration vs. Work" in Microsoft Project.
Answer:
Duration refers to the total time span needed to complete a task, while Work is the total amount of effort or labor required. Duration can be affected by the number of resources assigned, while Work is constant.
Question:
Explain the "Earned Value Management" (EVM) concept in Microsoft Project.
Answer:
EVM is a project management technique used to assess project performance by comparing planned progress (Planned Value) with actual progress (Earned Value) and cost performance (Actual Cost).
Question:
Explain the "Resource Leveling" process in Microsoft Project.
Answer:
Resource Leveling is the process of adjusting the start and finish dates of tasks to balance resource allocation and avoid overallocation. It helps in optimizing resource usage across the project.
Question:
Explain the "Task Status" options available in Microsoft Project.
Answer:
Task Status options include "Not Started," "In Progress," and "Completed." These options help track the progress of tasks and update the project's schedule based on the completion status of each task.
Question:
Explain the "Work Contour" feature and its impact on project scheduling.
Answer:
Work Contour allows users to define how work is distributed over time for a task, such as spreading work evenly, concentrating it at certain periods, or applying custom distribution patterns.
Question:
Explain the concept of "Resource Contouring" in Microsoft Project.
Answer:
Resource Contouring adjusts the distribution of work over time to reflect realistic resource availability and usage patterns. It helps in planning and optimizing resource allocation throughout the project.
Question:
Explain the function of "Task Usage View" in Microsoft Project.
Answer:
The Task Usage View provides detailed information on task assignments and resource allocations. It shows how resources are assigned to tasks and how much work has been completed versus what is remaining.
Question:
Explain the role of the "Timeline View" in Microsoft Project.
Answer:
The Timeline View provides a high-level overview of the project schedule, showing key tasks, milestones, and their durations in a graphical format. It is useful for summarizing and communicating project progress.
Question:
Explain what a Gantt Chart represents in Microsoft Project.
Answer:
A Gantt Chart visually represents the schedule of tasks in a project. It shows tasks along a timeline, displaying their start and end dates, duration, and dependencies.
Question:
How do "Cost Resources" differ from "Work Resources" in Microsoft Project?
Answer:
Cost Resources represent costs associated with specific tasks or project phases, without requiring work effort, while Work Resources are human or equipment resources that perform work on tasks.
Question:
How do "Milestone Tasks" differ from regular tasks in Microsoft Project?
Answer:
Milestone Tasks are tasks with zero duration that represent significant events or achievements in the project. They are used to mark key dates and deliverables but do not have actual work associated with them.
Question:
How do "Task Priorities" impact resource allocation in Microsoft Project?
Answer:
Higher Task Priorities indicate more critical tasks that should be addressed first during resource allocation and scheduling, ensuring that essential tasks receive the necessary resources and attention.
Question:
How do you create a Baseline in Microsoft Project?
Answer:
A Baseline is created by saving the original project plan as a reference point. This is done by navigating to the "Project" tab, selecting "Set Baseline," and choosing the baseline options to save.
Question:
How does "Task Dependency" affect the project schedule in Microsoft Project?
Answer:
Task Dependencies determine the order in which tasks are performed and how delays in one task can impact subsequent tasks. They are crucial for creating an accurate and realistic project schedule.
Question:
How does "Task Splitting" work in Microsoft Project?
Answer:
Task Splitting allows a task to be broken into segments with breaks in between. This helps in managing tasks that cannot be worked on continuously due to constraints or dependencies.
Question:
How does Microsoft Project calculate "Task Duration"?
Answer:
Task Duration is calculated based on the number of workdays required to complete a task, taking into account the working hours and calendar settings defined for the task.
Question:
How does Microsoft Project handle "Resource Over-allocation"?
Answer:
Microsoft Project identifies resource over-allocation by comparing the amount of work assigned to a resource against its available capacity. It provides options to resolve over-allocation, such as leveling or redistributing work.
Question:
How does Microsoft Project handle "Task Constraints" and what are their types?
Answer:
Task Constraints in Microsoft Project impose specific scheduling restrictions on tasks. Types include "Start No Earlier Than," "Finish On," "Must Start On," and "Must Finish On," each affecting task scheduling differently.
Question:
How does Microsoft Project handle task dependencies?
Answer:
Task dependencies are managed using relationships like Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF). These relationships define how tasks are linked and affect scheduling.
Question:
How is "Cost Rate Table" used in Microsoft Project?
Answer:
The Cost Rate Table defines different cost rates for resources based on various factors such as hours worked or different time periods. It helps in calculating project costs accurately based on resource rates.
Question:
How is "Task Assignment" different from "Task Resource" in Microsoft Project?
Answer:
Task Assignment refers to the process of linking resources to specific tasks, while Task Resource refers to the actual resources (human, equipment, etc.) used to perform the task.
Question:
How is "Work" different from "Effort" in Microsoft Project?
Answer:
Work refers to the total amount of labor required to complete a task, usually measured in hours. Effort refers to the actual time resources spend working on the task, which can vary based on resource availability.
Question:
What are "Task Constraints" and how do they affect scheduling in Microsoft Project?
Answer:
Task Constraints are specific rules or limitations applied to tasks, such as "Must Start On" or "Finish No Later Than." They can restrict scheduling flexibility and impact the project's critical path.
Question:
What does "Critical Path" indicate in a project schedule?
Answer:
The Critical Path is the sequence of tasks that determines the shortest time to complete the project. Tasks on this path have no slack, and any delay will directly impact the project's finish date.
Question:
What does "Effort-Driven Scheduling" mean in Microsoft Project?
Answer:
Effort-Driven Scheduling adjusts task duration based on changes in resource allocation. If resources are added or removed, the duration of the task changes accordingly to maintain the effort required.
Question:
What does "Fixed Duration" mean and how does it affect task scheduling?
Answer:
Fixed Duration means that the duration of a task remains constant regardless of changes in resource assignment or work effort. Adjusting the number of resources will not affect the task's duration.
Question:
What does "Project Status Report" include in Microsoft Project?
Answer:
A Project Status Report typically includes information on project progress, task completion, resource usage, schedule adherence, and any issues or risks impacting the project.
Question:
What does "Schedule Compression" mean and how is it applied in Microsoft Project?
Answer:
Schedule Compression involves techniques like Crashing or Fast Tracking to shorten the project duration. Crashing adds additional resources, while Fast Tracking overlaps tasks to accelerate project completion.
Question:
What does the term "Float" or "Slack" mean in Microsoft Project?
Answer:
Float or Slack is the amount of time that a task can be delayed without affecting the project's end date or the start date of subsequent tasks. It helps in scheduling flexibility.
Question:
What is "Auto-Schedule" and how does it differ from "Manually Scheduled" tasks?
Answer:
Auto-Schedule automatically adjusts task start and end dates based on changes in task dependencies and resource availability. Manually Scheduled tasks require users to manually adjust dates and durations.
Question:
What is "Milestone Tracking" and how is it used in Microsoft Project?
Answer:
Milestone Tracking involves monitoring the completion of significant project milestones. It helps measure progress against key deliverables and ensure that important deadlines are met.
Question:
What is "Project Baseline" and why is it important?
Answer:
A Project Baseline is a snapshot of the project’s original plan, including scope, schedule, and costs. It is used as a reference to measure project performance and compare planned versus actual progress.
Question:
What is "Timephased Data" and how is it utilized in Microsoft Project?
Answer:
Timephased Data represents information (e.g., work, cost) broken down by time periods, such as days or weeks. It is used to track and analyze project performance over time, providing detailed insights into progress.
Question:
What is a "Constraint" in Microsoft Project?
Answer:
A Constraint is a restriction placed on a task that affects its scheduling. Examples include "Start No Earlier Than" or "Finish On," which dictate specific conditions under which a task must be completed.
Question:
What is a "Task Dependency" and how is it set in Microsoft Project?
Answer:
A Task Dependency defines the relationship between two tasks, indicating how one task affects the start or finish of another. It is set by linking tasks with specific dependency types (FS, SS, FF, SF).
Question:
What is Critical Path Method (CPM) in Microsoft Project?
Answer:
CPM is a project management technique used to determine the longest path of dependent tasks and calculate the shortest possible project duration. Tasks on this path are critical and determine the project timeline.
Question:
What is the "Resource Allocation" and how is it tracked?
Answer:
Resource Allocation refers to the assignment of resources to tasks. It is tracked by monitoring the amount of work assigned to each resource, their availability, and ensuring resources are not over-allocated.
Question:
What is the "Resource Sheet" used for in Microsoft Project?
Answer:
The Resource Sheet is used to enter and manage information about resources, including their names, types, rates, and availability. It is a key component for resource management and allocation.
Question:
What is the "Resource Usage" view and how is it beneficial?
Answer:
The Resource Usage view displays the work assignments of resources across tasks and time periods. It helps in managing and balancing resource workload, tracking assignments, and identifying potential conflicts.
Question:
What is the "Task Calendar" and how does it influence task scheduling?
Answer:
The Task Calendar defines specific working and non-working times for individual tasks. It overrides the default project calendar and allows for more precise scheduling based on task-specific requirements.
Question:
What is the "Task Details Form" used for in Microsoft Project?
Answer:
The Task Details Form provides an in-depth view of task-specific information, such as task duration, dependencies, and assigned resources. It is used for detailed task management and adjustments.
Question:
What is the "Team Planner View" and how does it help in project management?
Answer:
The Team Planner View shows resource assignments and their workload in a calendar format, helping managers identify over-allocations, plan resource distribution, and adjust assignments for balanced workload.
Question:
What is the difference between "Fixed Units" and "Fixed Duration" task types in Microsoft Project?
Answer:
Fixed Units means that the number of resources assigned to a task remains constant while the task duration can change. Fixed Duration means that the task duration remains constant while the number of resources can change.
Question:
What is the difference between a Task and a Milestone in Microsoft Project?
Answer:
A Task is an activity that needs to be accomplished within a project, whereas a Milestone is a significant event or checkpoint in the project timeline, often marking the completion of a phase.
Question:
What is the function of "Baseline Work" and how is it different from "Actual Work"?
Answer:
Baseline Work represents the original amount of work planned for a task. Actual Work is the real amount of work completed. Comparing these helps in tracking performance and identifying deviations from the plan.
Question:
What is the function of "Resource Leveling" in managing project schedules?
Answer:
Resource Leveling adjusts the start and finish dates of tasks to resolve conflicts and ensure that resource usage is balanced throughout the project, preventing overallocation and optimizing resource use.
Question:
What is the function of "Task Notes" in Microsoft Project?
Answer:
Task Notes provide a space to add additional information or comments related to a specific task. They can include instructions, observations, or details that help in task management and communication.
Question:
What is the purpose of "Project Summary Task"?
Answer:
The Project Summary Task is a special task that represents the entire project. It aggregates information from all tasks and provides an overview of project start and end dates, overall duration, and completion status.
Question:
What is the purpose of a Work Breakdown Structure (WBS) in Microsoft Project?
Answer:
The WBS is used to break down a project into smaller, manageable components or tasks. It helps in organizing and defining the total scope of the project, providing a structure for planning and control.
Question:
What is the purpose of the Resource Pool in Microsoft Project?
Answer:
A Resource Pool is a shared list of resources available for use across multiple projects. It allows for efficient management and allocation of resources across projects to avoid overallocation.
Question:
What is the role of "Resource Leveling Delay" and how does it impact project scheduling?
Answer:
Resource Leveling Delay is the amount of time that tasks are delayed to resolve resource conflicts. It helps in balancing resource usage and preventing overallocation, but may extend the project schedule.
Question:
What is the significance of "Task Priority" in Microsoft Project?
Answer:
Task Priority determines the importance of tasks when scheduling. Higher-priority tasks are given precedence over lower-priority tasks in scheduling and resource allocation, especially during resource leveling.